Site-readiness sheet
- Print-ready HTML for Site-readiness sheet
- Markdown for Site-readiness sheet
- CSV for Site-readiness sheet
Free to use inside your own organization; redistribution not permitted.

Repair and installation
Prepare a room and its power, and plan an installation and its qualification, with a site-readiness checklist you can export.
A checklist to prepare a room and its services before an installation or move, to be completed against your manufacturer's documents.
The checklist tells you what to find out. The values come from your manufacturer's documents, and you type them in.
In the public pages we checked on 24 November 2026, we could not find a pre-installation guide, an installation checklist, a service manual or a parts list.[1] Size, weight and power figures for these instruments appear only in third-party listings, and we do not republish them.
So each line below asks you to record the requirement as written in your manufacturer’s own site-preparation document, then set a status, name the evidence and an owner, and date it. If you do not hold that document, ask the manufacturer for it in writing and record who answered.
Fifteen lines in four groups. Your answers stay in this browser unless you choose to download or print them.
0 of 15 lines have a status0 met0 not met
Access route and doors
Trace the route from the delivery point to the final position. Record door, corridor and lift measurements and compare them with the dimensions in your manufacturer's document.
Lifting and handling
Record who moves the unit, with what equipment, and who signs off the route. Handling instructions come from the manufacturer or the engineer, not from this sheet.
Bench or floor support
Note the surface the unit will stand on and whether its load rating is documented. Compare it with the load figure in your manufacturer's document.
Electrical supply and protection
Record the supply, circuit protection and earthing as your electrician or facilities team documents them, then compare each with your manufacturer's document. See the power-quality note.
Network and PC
Record where the instrument PC will sit, how it connects to the network and who maintains that network.
Exhaust and ventilation as specified in the manufacturer's site-preparation document
Ask the manufacturer for that document in writing. Record who confirmed the arrangement and when.
Waste handling
Record how waste is collected, stored and removed under your biosafety rules.
Ambient conditions
Record how room temperature and humidity are controlled and monitored, and compare them with the ranges in your manufacturer's document.
Vibration and dust
Note nearby sources of vibration and how dust is controlled in the room.
Kit storage
Record where reagents and consumables are stored, as each supplier's insert states.
Contamination-control zones
Record how pre-PCR and post-PCR work are separated and how people and materials move between areas.
Safety signage
Record the signage your site requires at and near the instrument.
Engineer access
Record clear space around the unit, parking and building access for the engineer, and the name of the customer representative who will be present.
Decontamination status
Name the person who will sign the decontamination declaration and the date it will be signed.
Documentation held
List the manufacturer documents you hold lawfully, with their versions. We do not supply them.
Networking and waste disposal are customer responsibilities under the manufacturer’s warranty, along with data backup and periodic maintenance[2]. Settle who owns each before the visit.
Public laboratory guidance recommends one-way workflow that separates pre-PCR work from post-PCR work, with at least three rooms or physical separation by dead-air boxes or PCR workstations; CDC reports that CLIA requires one-way workflow for open amplification systems[3]. This is general good practice, not a manufacturer requirement.
See the power-quality note for what to record about your supply.
Free to use inside your own organization; redistribution not permitted.
Send your completed checklist with a request for installation, or ask a question first. Request service
Why mains power quality matters for sensitive instruments, and what to record and ask your facilities team.
Mass spectrometers and the PCs that run them are sensitive electronic equipment.
As a matter of general good practice, interruptions and disturbances in the supply can stop a run, upset a connected PC or leave data in an uncertain state. They are also hard to diagnose afterwards if nobody wrote them down. A short, dated record of what happened in the room is often the quickest route to a clear answer.
We state no supply requirement here. In the public pages we checked on 24 November 2026, we could not find a site-preparation guide from the manufacturer. Electrical figures for the Analyzer 4 appear only in third-party listings[1]. Take every requirement from your manufacturer’s own document.
Your electrician or facilities team can usually supply most of this in one sitting.
A printable sheet. Put these to the manufacturer in writing and file the answers with your site-readiness checklist.
How installation and qualification tasks are executed and documented against your protocol or documents you supply.
Twelve steps in three lanes. Three of them are hold points where work waits for a decision.
A common framework treats analytical instrument qualification as design (DQ), installation (IQ), operational (OQ) and performance (PQ) stages, and sorts instruments into groups by how much qualification they need[4].
We execute and document qualification tasks against your protocol or documents you supply. We do not set acceptance criteria and we do not declare an instrument validated or fit for clinical use.
Installation planning and execution with you, working from the manufacturer's documents and your protocol, with a written record.
Regions: United States, Germany Lead time: Confirmed at triage.
Running and recording installation and operational qualification tasks against your protocol or the documents you supply. You set the acceptance criteria.
Regions: United States, Germany Lead time: Confirmed at triage.
One vendor publishes a pattern. Use it as a prompt for your own change control, not as a rule.
A pattern from another vendor; your SOP and the manufacturer's documents decide
In that vendor’s pattern, IQ is repeated at installation, after relocation and re-installation, and after an environment change. OQ follows reactive service, a software upgrade or preventive maintenance. PQ follows a qualified major repair[5]. Qualification after service is a common pattern across instrument makers[6].
Choose an event to see the pattern for it.
| Event | IQ | OQ | PQ |
|---|---|---|---|
| New installation | In the pattern | Not stated | Not stated |
| Relocation and re-installation | In the pattern | Not stated | Not stated |
| Change to the environment | In the pattern | Not stated | Not stated |
| Software upgrade | Not stated | In the pattern | Not stated |
| Reactive service (after a fault) | Not stated | In the pattern | Not stated |
| Preventive maintenance | Not stated | In the pattern | Not stated |
| Qualified major repair | Not stated | Not stated | In the pattern |
The manufacturer’s service plans name qualification services and performance verification kits and define neither[7]. In the public pages we checked on 24 November 2026, we could not find a qualification protocol or an installation checklist.[1] If you need the protocol the manufacturer uses, ask the manufacturer.
What you should hold when the job ends.
What you provide
What you receive
Free to use inside your own organization; redistribution not permitted.
Free to use inside your own organization; redistribution not permitted.
See service reports and records for the report itself.
Ask for an installation, or send your site-readiness checklist and documents list first. Request service
Continues on Plan an instrument move: the move plan and checklist, and on Buy used or retire an instrument: the pre-purchase and decommissioning checklists.
Covers stay closed. Work inside an instrument is for a qualified service engineer only. Safety statement
Research-use context. No diagnostic or clinical claims. Read the research-use notice
Describe the instrument and what you need. Leave out patient and sample data.
[1]
INS-01
We could not find a pre-installation guide, installation checklist, IQ/OQ protocol, service manual or parts list in the Agena support and resource pages we checked on 24 November 2026; what is there is warranty terms, two service plans and support routes. Physical and electrical figures for the Analyzer 4 appear only in third-party listings.
Agena Bioscience: Support; Agena Bioscience: Product Literature, agenabio.com/support/
Checked on 24 November 2026Derivedmedium confidence
[2]
WAR-03
The warranty page makes these customer responsibilities: periodic maintenance and calibration, replacing hardware components such as dispense pins, liquid-handler tips and clean resin tools, data backup, networking and waste disposal. Lasers are excepted, so laser replacement is not a customer task.
Agena Bioscience: System Warranty, agenabio.com/support/system-warranty/
Checked on 24 November 2026Manufacturer-reportedmedium confidence
[3]
LAB-19
APHL guidance on molecular laboratory space recommends unidirectional workflow separating pre-PCR stages, at least three enclosed rooms (reagents; sample preparation and assay setup; PCR and post-amplification) or physical separation using dead-air boxes or PCR workstations, and positive air pressure in reagent rooms. CDC's MMWR says CLIA requires unidirectional workflow with separate areas for specimen preparation, amplification and detection for open amplification systems; closed systems are exempt.
APHL: Molecular Workflow (newborn screening resources); CDC MMWR Recommendations and Reports 58(RR-6), aphl.org/programs/newborn_screening/Pages/Molecular-Workflow.aspx
Checked on 24 November 2026Third partymedium confidence
[4]
LAB-16
USP general chapter <1058> frames analytical instrument qualification as DQ, IQ, OQ and PQ, with instruments sorted into groups A, B and C; a draft revision renames it Analytical Instrument and System Qualification.
An Enhanced Approach to Analytical Instrument and System Qualification (Spectroscopy, 1 May 2025), spectroscopyonline.com/an-enhanced-approach-to-analytical-instrument-and-system-qualification
Checked on 24 November 2026Third partymedium confidence
[5]
LAB-17
Another instrument vendor's public qualification pattern: IQ confirms installation to specification and safety rules, OQ confirms operation within operating specifications, and PQ follows a qualified major repair. IQ is repeated at install, after relocation and reinstallation and after environment change; OQ after reactive service, software upgrade or preventive maintenance.
Instrument qualification services page (another instrument vendor), Other-vendor public page
Checked on 24 November 2026Third partymedium confidence
[6]
DIA-06
Qualification after service is a common pattern: another vendor lists operational qualification after reactive service or preventive maintenance and performance qualification after a qualified major repair, while Agena's Plus plan names monthly performance verification kits and qualification services without defining them.
Instrument qualification services page (another instrument vendor); Agena Bioscience: Service Plans, Other-vendor public page
Checked on 24 November 2026Derivedmedium confidence
[7]
SUP-01
Agena's service-plan page lists an Essential tier (preventive maintenance, on-site applications support, fast response) and a Plus tier that adds applications training, monthly performance verification kits, next-day response and qualification services. Both cover the system and the Chip Prep Module; no prices, hours or definitions are given.
Agena Bioscience: Service Plans, agenabio.com/support/service-plans/
Checked on 24 November 2026Manufacturer-reportedmedium confidence