Repair and installation

Site readiness and installation

Prepare a room and its power, and plan an installation and its qualification, with a site-readiness checklist you can export.

Checked on 24 November 2026
On this page

Site-readiness checklist

A checklist to prepare a room and its services before an installation or move, to be completed against your manufacturer's documents.

Why this checklist has no numbers

The checklist tells you what to find out. The values come from your manufacturer's documents, and you type them in.

In the public pages we checked on 24 November 2026, we could not find a pre-installation guide, an installation checklist, a service manual or a parts list.[1] Size, weight and power figures for these instruments appear only in third-party listings, and we do not republish them.

So each line below asks you to record the requirement as written in your manufacturer’s own site-preparation document, then set a status, name the evidence and an owner, and date it. If you do not hold that document, ask the manufacturer for it in writing and record who answered.

How to use it

  1. Work through every line. Use Not applicable only where you can say why.
  2. Type the requirement exactly as your document states it, with the document and version in the evidence box.
  3. Leave a line Not met until the evidence exists. Open lines are normal before a visit.
  4. Download or print the result and send it with your request. Nothing here is sent for you.
Room plan with ten readiness zonesA plain room outline holding ten numbered zones: access route and doors, lifting and handling, bench or floor support, electrical supply and protection, network and PC, exhaust and ventilation, waste handling, kit storage, ambient conditions and engineer access. Each zone has an empty tag for a value taken from the manufacturer's document.1Access routeand doors2Lifting and handling3Bench orfloor support4Electrical supplyand protection5Network and PC6Exhaust andventilation7Waste handling8Kit storage9Ambient conditions10Engineer access
Generic room plan. Ten zones; each dashed tag is left empty because the value comes from your manufacturer's document.
  1. Access route and doors
  2. Lifting and handling
  3. Bench or floor support
  4. Electrical supply and protection
  5. Network and PC
  6. Exhaust and ventilation
  7. Waste handling
  8. Kit storage
  9. Ambient conditions
  10. Engineer access

The checklist

Fifteen lines in four groups. Your answers stay in this browser unless you choose to download or print them.

0 of 15 lines have a status0 met0 not met

Getting it in

  • Access route and doors

    Trace the route from the delivery point to the final position. Record door, corridor and lift measurements and compare them with the dimensions in your manufacturer's document.

  • Lifting and handling

    Record who moves the unit, with what equipment, and who signs off the route. Handling instructions come from the manufacturer or the engineer, not from this sheet.

  • Bench or floor support

    Note the surface the unit will stand on and whether its load rating is documented. Compare it with the load figure in your manufacturer's document.

Services

  • Electrical supply and protection

    Record the supply, circuit protection and earthing as your electrician or facilities team documents them, then compare each with your manufacturer's document. See the power-quality note.

  • Network and PC

    Record where the instrument PC will sit, how it connects to the network and who maintains that network.

  • Exhaust and ventilation as specified in the manufacturer's site-preparation document

    Ask the manufacturer for that document in writing. Record who confirmed the arrangement and when.

  • Waste handling

    Record how waste is collected, stored and removed under your biosafety rules.

The room

  • Ambient conditions

    Record how room temperature and humidity are controlled and monitored, and compare them with the ranges in your manufacturer's document.

  • Vibration and dust

    Note nearby sources of vibration and how dust is controlled in the room.

  • Kit storage

    Record where reagents and consumables are stored, as each supplier's insert states.

  • Contamination-control zones

    Record how pre-PCR and post-PCR work are separated and how people and materials move between areas.

  • Safety signage

    Record the signage your site requires at and near the instrument.

People and paperwork

  • Engineer access

    Record clear space around the unit, parking and building access for the engineer, and the name of the customer representative who will be present.

  • Decontamination status

    Name the person who will sign the decontamination declaration and the date it will be signed.

  • Documentation held

    List the manufacturer documents you hold lawfully, with their versions. We do not supply them.

Notes on particular lines

Network and waste

Networking and waste disposal are customer responsibilities under the manufacturer’s warranty, along with data backup and periodic maintenance[2]. Settle who owns each before the visit.

Contamination-control zones

Public laboratory guidance recommends one-way workflow that separates pre-PCR work from post-PCR work, with at least three rooms or physical separation by dead-air boxes or PCR workstations; CDC reports that CLIA requires one-way workflow for open amplification systems[3]. This is general good practice, not a manufacturer requirement.

Power

See the power-quality note for what to record about your supply.

What we will ask for

  • The completed checklist, with the requirement for each line copied from your manufacturer’s document.
  • The list of manufacturer documents you hold lawfully, with versions.
  • The name of the customer representative who will be present, and the person who signs the decontamination declaration.
  • Photographs of the room and the access route, with no patient, sample or personal data visible.

Send your completed checklist with a request for installation, or ask a question first. Request service

Power-quality note

Why mains power quality matters for sensitive instruments, and what to record and ask your facilities team.

Why it matters

Mass spectrometers and the PCs that run them are sensitive electronic equipment.

As a matter of general good practice, interruptions and disturbances in the supply can stop a run, upset a connected PC or leave data in an uncertain state. They are also hard to diagnose afterwards if nobody wrote them down. A short, dated record of what happened in the room is often the quickest route to a clear answer.

We state no supply requirement here. In the public pages we checked on 24 November 2026, we could not find a site-preparation guide from the manufacturer. Electrical figures for the Analyzer 4 appear only in third-party listings[1]. Take every requirement from your manufacturer’s own document.

What to record

Your electrician or facilities team can usually supply most of this in one sitting.

  • Outages: date, time, how long, what failed.
  • Sags and surges you noticed: lights dimming, equipment resetting, alarms on other equipment.
  • Who supplies the room: the circuit, the board, and whether the circuit is shared with large equipment such as freezers, autoclaves or air handling.
  • Protection in place: breakers, residual-current devices, surge protection, and when each was last tested.
  • Earthing: who tested it, when, and where the record is held.
  • Backup or conditioned power already installed, and what it feeds.
  • Work planned on the building supply in the coming months.

Questions for the manufacturer

A printable sheet. Put these to the manufacturer in writing and file the answers with your site-readiness checklist.

Question sheetprint it, write the answers on it
  1. What supply does the instrument need? Please send the requirement in your site-preparation document.
  2. What circuit protection and earthing does it need?
  3. Do you advise surge protection or backup power for the instrument? If so, what, and where do you describe it?
  4. Do you advise the same for the instrument PC and the chip-prep unit?
  5. What should we do about the instrument and PC before a planned power outage?
  6. Who confirms, in writing, that the room meets the requirement?
Open the site-readiness checklist

What we will ask for

  • Your dated record of outages and disturbances, if any.
  • The electrician’s or facilities team’s evidence for supply, protection and earthing, as they hold it.
  • The manufacturer’s written answers to the questions above.

Installation and qualification

How installation and qualification tasks are executed and documented against your protocol or documents you supply.

From request to a documented instrument

Twelve steps in three lanes. Three of them are hold points where work waits for a decision.

Installation and qualification flowTwelve steps across three lanes: customer, engineer, and laboratory director or QA. Hold points sit at site-readiness sign-off, the decontamination declaration and PQ.CustomerEngineerLab director or QAOuter ring: hold point, work waits here1Request and scoping2Documentation collection3Site-readiness sign-off4Delivery and inspection5Decontamination declaration6Installation7Power-up and softwareconfiguration8Functional checks per themanufacturer's documents9IQ record10OQ per your protocol11PQ by your validation runs12Handover and records
Shape marks the lane. Outer ring marks a hold point.
  1. Customer: Request and scoping
  2. Customer: Documentation collection
  3. Lab director or QA: Site-readiness sign-off (hold point)
  4. Engineer: Delivery and inspection
  5. Customer: Decontamination declaration (hold point)
  6. Engineer: Installation
  7. Engineer: Power-up and software configuration
  8. Engineer: Functional checks per the manufacturer's documents
  9. Engineer: IQ record
  10. Lab director or QA: OQ per your protocol
  11. Lab director or QA: PQ by your validation runs (hold point)
  12. Customer: Handover and records
  1. Step 1: Request and scoping

    You describe what is being installed and where. We confirm which units are involved and what is out of scope.
  2. Step 2: Documentation collection

    You gather the manufacturer documents you hold lawfully. We work from those and your own protocol; we do not supply them.
  3. Step 3: Site-readiness sign-off

    The completed site-readiness checklist is signed off by the person your procedure names. Open lines are listed, not hidden.
  4. Step 4: Delivery and inspection

    The delivery is inspected against the packing list, serial numbers are recorded as printed, and condition photographs are filed.
  5. Step 5: Decontamination declaration

    A signed declaration is on file before any engineer handles a unit that has been used before.
  6. Step 6: Installation

    An engineer installs, where the installation line is on offer. Your named representative is present throughout.
  7. Step 7: Power-up and software configuration

    Software and operating-system names and versions are recorded as shown on the PC.
  8. Step 8: Functional checks

    Checks are carried out as your manufacturer's documents specify. The record names the document and the values, and judges neither.
  9. Step 9: IQ record

    The installation qualification record is completed, with the reference of each document the checks came from.
  10. Step 10: OQ per your protocol

    Operational qualification tasks are executed and recorded against the protocol you hold. Acceptance criteria are yours.
  11. Step 11: PQ by your validation runs

    Performance qualification is your laboratory's own work with your own materials. We can record the runs you perform.
  12. Step 12: Handover and records

    The records pack, the service report and the operator handover are filed with your quality records.

What qualification means here

A common framework treats analytical instrument qualification as design (DQ), installation (IQ), operational (OQ) and performance (PQ) stages, and sorts instruments into groups by how much qualification they need[4].

We execute and document qualification tasks against your protocol or documents you supply. We do not set acceptance criteria and we do not declare an instrument validated or fit for clinical use.

Installationscope

Installation planning and execution with you, working from the manufacturer's documents and your protocol, with a written record.

Regions: United States, Germany Lead time: Confirmed at triage.

Qualification recordsscope

Running and recording installation and operational qualification tasks against your protocol or the documents you supply. You set the acceptance criteria.

Regions: United States, Germany Lead time: Confirmed at triage.

When qualification is usually repeated

One vendor publishes a pattern. Use it as a prompt for your own change control, not as a rule.

A pattern from another vendor; your SOP and the manufacturer's documents decide

In that vendor’s pattern, IQ is repeated at installation, after relocation and re-installation, and after an environment change. OQ follows reactive service, a software upgrade or preventive maintenance. PQ follows a qualified major repair[5]. Qualification after service is a common pattern across instrument makers[6].

Choose an event to see the pattern for it.

Events against IQ, OQ and PQ in one vendor’s published pattern
EventIQOQPQ
New installationIn the patternNot statedNot stated
Relocation and re-installationIn the patternNot statedNot stated
Change to the environmentIn the patternNot statedNot stated
Software upgradeNot statedIn the patternNot stated
Reactive service (after a fault)Not statedIn the patternNot stated
Preventive maintenanceNot statedIn the patternNot stated
Qualified major repairNot statedNot statedIn the pattern

What the manufacturer says publicly

The manufacturer’s service plans name qualification services and performance verification kits and define neither[7]. In the public pages we checked on 24 November 2026, we could not find a qualification protocol or an installation checklist.[1] If you need the protocol the manufacturer uses, ask the manufacturer.

The records pack

What you should hold when the job ends.

What you provide

  • The documents you hold lawfully, with versions
  • The completed site-readiness checklist
  • Your qualification protocol and acceptance criteria
  • A named representative and the declaration signatory

What you receive

  • An installation checklist, completed
  • An IQ record, and OQ records where a protocol applies
  • An evidence index listing where each record sits
  • A written service report that records results and does not judge them

See service reports and records for the report itself.

Ask for an installation, or send your site-readiness checklist and documents list first. Request service

Continues on Plan an instrument move: the move plan and checklist, and on Buy used or retire an instrument: the pre-purchase and decommissioning checklists.

Notices

Covers stay closed. Work inside an instrument is for a qualified service engineer only. Safety statement

Research-use context. No diagnostic or clinical claims. Read the research-use notice

Ready to ask?

Describe the instrument and what you need. Leave out patient and sample data.

Request service

Sources

  1. [1]
    INS-01

    We could not find a pre-installation guide, installation checklist, IQ/OQ protocol, service manual or parts list in the Agena support and resource pages we checked on 24 November 2026; what is there is warranty terms, two service plans and support routes. Physical and electrical figures for the Analyzer 4 appear only in third-party listings.

    Agena Bioscience: Support; Agena Bioscience: Product Literature, agenabio.com/support/

    Checked on 24 November 2026Derivedmedium confidence

  2. [2]
    WAR-03

    The warranty page makes these customer responsibilities: periodic maintenance and calibration, replacing hardware components such as dispense pins, liquid-handler tips and clean resin tools, data backup, networking and waste disposal. Lasers are excepted, so laser replacement is not a customer task.

    Agena Bioscience: System Warranty, agenabio.com/support/system-warranty/

    Checked on 24 November 2026Manufacturer-reportedmedium confidence

  3. [3]
    LAB-19

    APHL guidance on molecular laboratory space recommends unidirectional workflow separating pre-PCR stages, at least three enclosed rooms (reagents; sample preparation and assay setup; PCR and post-amplification) or physical separation using dead-air boxes or PCR workstations, and positive air pressure in reagent rooms. CDC's MMWR says CLIA requires unidirectional workflow with separate areas for specimen preparation, amplification and detection for open amplification systems; closed systems are exempt.

    APHL: Molecular Workflow (newborn screening resources); CDC MMWR Recommendations and Reports 58(RR-6), aphl.org/programs/newborn_screening/Pages/Molecular-Workflow.aspx

    Checked on 24 November 2026Third partymedium confidence

  4. [4]
    LAB-16

    USP general chapter <1058> frames analytical instrument qualification as DQ, IQ, OQ and PQ, with instruments sorted into groups A, B and C; a draft revision renames it Analytical Instrument and System Qualification.

    An Enhanced Approach to Analytical Instrument and System Qualification (Spectroscopy, 1 May 2025), spectroscopyonline.com/an-enhanced-approach-to-analytical-instrument-and-system-qualification

    Checked on 24 November 2026Third partymedium confidence

  5. [5]
    LAB-17

    Another instrument vendor's public qualification pattern: IQ confirms installation to specification and safety rules, OQ confirms operation within operating specifications, and PQ follows a qualified major repair. IQ is repeated at install, after relocation and reinstallation and after environment change; OQ after reactive service, software upgrade or preventive maintenance.

    Instrument qualification services page (another instrument vendor), Other-vendor public page

    Checked on 24 November 2026Third partymedium confidence

  6. [6]
    DIA-06

    Qualification after service is a common pattern: another vendor lists operational qualification after reactive service or preventive maintenance and performance qualification after a qualified major repair, while Agena's Plus plan names monthly performance verification kits and qualification services without defining them.

    Instrument qualification services page (another instrument vendor); Agena Bioscience: Service Plans, Other-vendor public page

    Checked on 24 November 2026Derivedmedium confidence

  7. [7]
    SUP-01

    Agena's service-plan page lists an Essential tier (preventive maintenance, on-site applications support, fast response) and a Plus tier that adds applications training, monthly performance verification kits, next-day response and qualification services. Both cover the system and the Chip Prep Module; no prices, hours or definitions are given.

    Agena Bioscience: Service Plans, agenabio.com/support/service-plans/

    Checked on 24 November 2026Manufacturer-reportedmedium confidence