Repair and installation

Plan an instrument move

Plan a move from the first call to re-qualification, with a staged timeline, a date planner and a checklist you can export.

Checked on 24 November 2026

The site-readiness checklist, the power-quality note and installation and qualification are on Site readiness and installation.

On this page

Move an instrument

Plan a move: who does what, the records to keep, and the checks that follow, with a move checklist you can export.

What to do first

Three things, in this order, before anyone touches the instrument.

  1. Read your own warranty and plan. The manufacturer’s warranty excludes a system moved from its original installation location by anyone other than the manufacturer or a provider the page leaves undefined[1]. That is a coverage exclusion, not a ban. Decide with your agreement in hand.
  2. Decide what moves. The analyzer, the chip-prep unit, any stand-alone dispenser and the instrument PC are separate items. Reagents, chips and biological material never travel with them.
  3. Prepare the destination. Complete the site-readiness checklist for the new room before a date is fixed.

A staged plan

Eight stages, with no durations asserted. Your engineer and your carrier set the dates.

Relocation timelineEight stages along a time axis: consultation; documentation and declaration; backup; de-installation with a warranty note; packing and insured transport; re-installation; re-qualification; records update.CustomerEngineerOuter ring: hold point, work waits here1Consultation2Documentation and declaration3Backup4De-installation (warranty note)5Packing and insured transport6Re-installation7Re-qualification8Records update
Shape marks who leads each stage. Outer ring marks a hold point.
  1. Customer: Consultation
  2. Customer: Documentation and declaration (hold point)
  3. Customer: Backup
  4. Engineer: De-installation (warranty note) (hold point)
  5. Engineer: Packing and insured transport
  6. Engineer: Re-installation
  7. Customer: Re-qualification
  8. Customer: Records update

Other instrument makers describe a move as a staged, insured job led by engineers: a consultation before the move, insured transport, de-installation and re-installation by engineers, then testing[4]. One of those descriptions is silent on decontamination, so we add a signed declaration as stage two.

De-installation and re-installation are for a qualified service engineer only: instruments contain a laser, high-voltage electronics and a vacuum system. Your own team never opens covers or disconnects internal parts to prepare a move.

After the move, which records are repeated is for your change control to decide. A pattern from another vendor; your SOP and the manufacturer's documents decide IQ is repeated after relocation and re-installation in that pattern[5]. See the full pattern.

Plan your dates

Enter the date for each stage. The planner checks that they run in order and prints the plan.

  1. Stage 1
  2. Stage 2
  3. Stage 3
  4. Stage 4
  5. Stage 5
  6. Stage 6
  7. Stage 7
  8. Stage 8

The planner checks only that dates run in order. It does not suggest dates or durations; those come from your engineer and your carrier.

Move checklist

0 of 14 lines have a status0 met0 not met

Plan

  • Scope agreed: what moves, from where, to where, and who decides

    Include the chip-prep unit, any stand-alone dispenser and the instrument PC if they move too.

  • Warranty and service-plan status checked and recorded

    Read your own agreement. A move by others can be a coverage exclusion.

  • Documents you hold lawfully gathered and listed

  • Destination room completed the site-readiness checklist

    Use the site-readiness sheet for the new room.

Before the move

  • Decontamination declaration signed and attached

    Signed by the customer before any visit. The engineer checks it against the visible condition of the unit.

  • Data and configuration backup made and checked

    Use the backup list in your manufacturer's guide.

  • Reagents, chips and biological material handled separately

    None of these travel with the instrument.

  • Customer representative named for de-installation and re-installation

The move

  • De-installation carried out by a qualified engineer

    Record the date, the engineer and any condition noted on the unit.

  • Packing as specified by the engineer

    Photograph the packed unit and keep the photographs with the record.

  • Insured transport booked, carrier and route recorded

After the move

  • Re-installation carried out by a qualified engineer

  • Re-qualification scope decided under your change control

    See the installation and qualification page for the pattern other instrument makers publish.

  • Records updated: location, asset register, service report filed

Moving across borders

A move between countries adds customs, transport and local regulatory questions that we cannot answer from a desk. Ask us early so the engineer, the carrier and your biosafety officer can agree the paperwork together.

Regions covered for moves: United States, Germany

The manufacturer’s warranty excludes relocation by others, while another vendor describes relocation as a staged, insured, engineer-led job followed by testing and re-qualification[2]. Plan for both.

Move an instrumentscope

Planning and support for moving an instrument, with checks recorded before and after the move.

We work only from protocols and documents the customer supplies and holds lawfully; we do not supply manufacturer protocols.

Regions: United States, Germany Lead time: Confirmed at triage.

Biosafety first

Describe the move: what, where from, where to, and when. Leave out patient and sample data. Request service

Continues on Buy used or retire an instrument: the pre-purchase checklist for a second-hand unit and the decommissioning checklist.

Notices

Covers stay closed. Work inside an instrument is for a qualified service engineer only. Safety statement

Research-use context. No diagnostic or clinical claims. Read the research-use notice

Ready to ask?

Describe the instrument and what you need. Leave out patient and sample data.

Request service

Sources

  1. [1]
    WAR-02

    The warranty page excludes a system that is repaired, modified, altered, assembled, disassembled or moved from its original installation location by anyone other than Agena or a service provider the page leaves undefined. It is a coverage exclusion, so customers should check their own agreement.

    Agena Bioscience: System Warranty, agenabio.com/support/system-warranty/

    Checked on 24 November 2026Manufacturer-reported

  2. [2]
    INS-03

    Agena's warranty excludes relocation by others from coverage, while another vendor describes relocation as a staged, insured, engineer-led job followed by testing and re-qualification (see LAB-17 and LAB-18).

    Agena Bioscience: System Warranty; How easy is it to relocate a mass spectrometer? (vendor community blog, 1 June 2017), agenabio.com/support/system-warranty/

    Checked on 24 November 2026Derivedmedium confidence

  3. [3]
    WAR-05

    Before a service visit the customer must tell Agena in writing about any decontamination of the system, a customer representative must be on site throughout on-site service, and no product or component may be returned without Agena's prior consent.

    Agena Bioscience: System Warranty, agenabio.com/support/system-warranty/

    Checked on 24 November 2026Manufacturer-reportedmedium confidence

  4. [4]
    LAB-18

    Relocation and return patterns at other instrument companies: one describes relocation in four stages (pre-move consultation, insured transport, de-installation and re-installation by engineers, testing and calibration) and is silent on decontamination; another requires a decontamination declaration form with some returns, a reference number, item condition and a detailed fault description.

    How easy is it to relocate a mass spectrometer? (vendor community blog, 1 June 2017); goods-return page (another instrument vendor), Other-vendor public page

    Checked on 24 November 2026Third partymedium confidence

  5. [5]
    LAB-17

    Another instrument vendor's public qualification pattern: IQ confirms installation to specification and safety rules, OQ confirms operation within operating specifications, and PQ follows a qualified major repair. IQ is repeated at install, after relocation and reinstallation and after environment change; OQ after reactive service, software upgrade or preventive maintenance.

    Instrument qualification services page (another instrument vendor), Other-vendor public page

    Checked on 24 November 2026Third partymedium confidence